Kemp-town Week 4

alexhunt New Project, Uncategorized Leave a Comment

So, another busy week on site - we have moved on now into the realms of “proper” building - construction of the new fabric. Having insulated the external walls with celotex, we are now floating in the suspended ceiling to the ground floor and also lifting the boarding of the living space above to prepare for the installation of the …

Kemp Town eco-renovation

alexhunt New Project Leave a Comment

So, continuing the theme of insulation as discussed last week - we have been using this week to insulate the exterior walls of the property - with 2 cross battened layers of Celotex (www.celotex.co.uk) thereby reducing cold bridging. (cold bridging is mostly succinctly described on Wikipedia - http://en.wikipedia.org/wiki/Cold_bridging) This insulation has been completed around the first floor, including behind the …

Insulating the exterior walls

alexhunt Bright Green News, New Project Leave a Comment

So this week we have finished the demolitions - the next step has been to begin the lining of the exterior front and rear walls with Poly-isocyanurate (PIR) insulation - now although this is not the most natural of materials (it is made from oil after all), it does have an extremely good thermal resistance (otherwise known as lamda - …

New Project week 2

alexhunt New Project Leave a Comment

just a quick update as things are moving on apace - we have removed the ceilings in the living room and kitchen - exposing the steels completely - it is amazing what a difference a few feet in height can make to a space. We have also stripped out the downstairs bathroom and airing cupboard - see photo below - …