So just a quick update… at the end ofour second week on site week we have managed to get the wall knocked out and the steel inserted to open up the dining and kitchen area – carefully insulated at the end of the beam to avoid cold bridging. This is to stop the beam creating a cold point running through …
New Project Part II
Our first week on the job was spent investigating what we couldn’t find out before; exactly what lay under the carpets, where the drains run, getting the water and gas turned off so we could start removing the existing bathroom and kitchen, having the electrician set up a site RCD (for safety), and discuss the electrical layout. With the help …